Question & Answer for the coating machine WIND-JF Series
1. Operational Requirements:
a. Machine Operators (#FTEs) Usually 2 ~ 4 Opeartors, accoding to your production per day,
b. Capacity 4000~5000pcs per day if you change the rotor types, 8000pcs per day if you produce one rotor type
c. Cycle time 1 meter to 2 meters per minuter of the screw rod
2. Technical Specifications:
a. Power Requirements: Detail the electrical specifications, including voltage, phase, and power consumption. --- 3Phase, your plant voltage is 480V?
b. Size of Machine (and how much space all equipment would need) 6m * 2.2m *1.5m , space needed 8m * 4m *
c. Tooling Changes: Is it possible to change tooling? --- Yes, 100sets toolings fr each rotor
3. Other:
-
Quality Checks: Required quality checks and any additional quality equipment needed. --- No
-
Maintenance: Specifications of the type of maintenance required, including frequency and duration --- No
-
Spare Parts Availability: Availability of spare parts and lead time for ordering --- Toolings
-
Training Needs: Specify the training requirements for operating the equipment, including time and cost. --- Yes, you send engineer to our plant
-
Auxiliary equipment needed to be able to use the machine --- No
-
Life span of machine?
4. Pay terms:
-
Delivery time --- 60 days after drawings and TT advance payment received
-
Place of delivery --- Shanghai Port
-
Freight cost to México --- Machine will be put in a 40''GP container, please inform your port name in Mexico